Friday, February 8, 2013

How to Prioritize a User Story Map

At the Agile 2012 conference, Serena Software surveyed attendees about their biggest agile challenge. Here was the top answer:

I don't know how accurate their results are but prioritizing customer demand was certainly a challenge for me on my first "agile" project.  We created a backlog with some pretty large user stories including "Search for items", "Maintain item attributes", "Set costs for items and groups", "Calculate prices", "Run pricing engine", etc. We then proceeded to tackle each story in order (that's what you do right?). After our first five week iteration (!!) we had created the most beautiful search screens you could possibly imagine. Our users could search by any and all combination of attributes and display the results in multiple different ways - there was even a brilliantly developed screen splitter so you could see all the extra details of one horizontal row in a vertical list at the right of the search results. We were so good that we finished our iteration commitment early and started to add in some of the nice-to-have search functionality. In truth, we were quite thrilled with our results. It was only in later iterations that the pit in our stomachs started to grow. While "Search for items" fit nicely into an iteration, "Maintain item attributes" had a tougher time and by the end we had lost all hope for "Run pricing engine". We had incredible search functionality (low priority) and sub par costing and pricing (high priority). Oops.

Thin slicing to the rescue!

It is no wonder that when Jeff Patton showed me how to create a user story map and use it to create thin application slices to prioritize agile projects effectively that I was hooked. It should also come as no surprise to you that in subsequent projects when "search" comes up as a feature request I am the first one to slice that story ruthlessly! "Search for items" is immediately sliced thinly to "Search by item number" and put in the first release. The rest of the search functionality is sliced into similarly sized user stories ("Search by description", "Search by customer item number", "Search by vendor", etc) and initially moved to the bottom of the story map.

Then we continue to slice each column in our user story map so that we can build a thin horizontal slice of our app in a short period of time (days or weeks). "Enter member, spouse, and dependent information" is sliced into "Enter member name" (first release), followed by "Enter member address", "Enter spouse information" and "Enter dependent information" in later releases of the application.



Prioritizing by risk and assumptions

Once you get the hang of ruthlessly slicing your stories and prioritizing them effectively in your map, you may notice a lot of 'easy' stories initially rise to the top of your priority list. In the case of "Search for items" this is a good thing. However, it can be dangerous to do all the easy stories first. When we've drafted our map and are ready to start prioritizing I like to ask - "Where are the risky stories? Where are our biggest assumptions?".

In the project example above, "Run Pricing Engine" was our riskiest story. It had some really aggressive performance requirements and if we couldn't meet those requirements then there was no point in building the application. In this case, choosing the 'easiest' slice of that feature would be a mistake - we should look for a slice that helps us validate our assumption that we can meet the performance requirements. Additionally, subsequent releases should continue to focus on that assumption before we work on stories like "Search by vendor".

Applying Cynefin to prioritization

This week I read an excellent article by Liz Keogh called "Cynefin for Developers". The article is well written and can help us understand how to apply Cynefin to project prioritization. One of the domains in the Cynefin model is "Complex" which Liz describes as:
"When you start writing tests, or having discussions, and the requirements begin changing underneath you because of what you discover as a result, that’s complex. You can look back at what you end up with and understand that it’s much better, but you can’t come up with it to start with, nor can you define what “better” will look like and try to reach it. It emerges as you work."

"... This is the land of high-feedback, risk and innovation: generally stuff you’ve never done before, anything that the business are unsure about, new technologies, etc."
As you are prioritizing your map, pay special attention to any stories that may fit into the Complex domain. Since these stories may change the direction of your project, I'd recommend that you tackle them earlier rather than later.

Re-prioritize often

Remember that priorities can and should change throughout your project as you learn more information. On a recent project we had a few stories that were identified as 'mandatory' but the team agreed to prioritize them towards the end of the project. Near the mid point of the project we brought in some of our external customers for a small focus group. We did a quick demo of our progress to date and also asked them to help us prioritize the remaining stories. We quickly learned that some of the previously 'mandatory' stories were no longer important and removed them from our backlog. Without that feedback and the willingness to change priorities at any point of the project we would have contributed to the famous Standish Report phrase: "64% of features are rarely or never used".

On a related note, if re-prioritization is going to happen frequently, then there isn't much point in prioritizing your whole map initially. A good rule of thumb is to prioritize the next one or two releases only. Even though prioritizing a story map can be a simple and fast exercise, it may be wasteful to slice and prioritize everything at the beginning.

In Summary

My secret recipe for prioritizing agile projects is simply this: Roll out your user story map; add some thinly sliced stories; stir in some prioritization by risk, assumption, and complexity; rinse and repeat.

Wednesday, December 26, 2012

Tips for Facilitating a User Story Mapping Session

In an earlier post I described how to create a user story map. Here are a few additional tips that you might find helpful.

Tip #1. Silent Brainstorming isn't mandatory. 
While using silent brainstorming is great for creating a map, you don't always need to use it. Sometimes you may find yourself in a situation where a full set of requirements has been written or the app is a re-write of an existing and well known application. In those cases I often skip the silent brainstorming and create the map from the existing documentation. Of course, I still do this with the team.

Tip #2. For your first map, reference the email map.
When you are creating your first map you may find that some people have difficulty finding the right level of detail for the second row in the map ("things people do" - the user tasks). In order to reduce the confusion walk them through the first two rows of the email map first. You can simply write the basic map on a few post-its as an example:

Finally, as they are writing their 'things people do', walk around and take a look at what they are writing. Encourage them when they are writing the correct level of detail ("Compose Email") and ask questions when they are getting into too much detail ("Set an email to High Priority").

Tip #3. Tear horizontally, not vertically
There are two ways to tear a post-it note off of the pad. If you tear it off horizontally (left to right or right to left) the post-it note will lie flat when it is stuck onto the wall. If you tear it off vertically (bottom to top) then it will have a curl.

Tip #4. Big Post-its
Quite often it isn't possible to create your map in the team room. If this is true for you then create your map on the large 3M Easel pads so that it can be transferred back to the team room.

Tip #5. Use name brand post-its
Post-its made by 3M seem to stick longer than other brands.

Wednesday, March 14, 2012

How to create a User Story Map

User story mapping is becoming a popular technique through the efforts of Jeff Patton and others that allows you to add a second dimension to your backlog. Here are a few reasons you should consider using this technique:
  • It allows you to see the big picture in your backlog.
  • It gives you a better tool for making decisions about grooming and prioritizing your backlog.
  • It promotes silent brainstorming and a collaborative approach to generating your user stories.
  • It encourages an iterative development approach where your early deliveries validate your architecture and solution.
  • It is a great visual alternative to traditional project plans.
  • It is a useful model for discussing and managing scope.
  • Allows you to visualize dimensional planning and real options for your project/product.

Want to hear more? I talked about the value and use of User Story Mapping with Richard and Carl on show #750 of DotNetRocks.

To create your own user story map:

1. Form a group of 3-5 people who understand the purpose of the product. 3-5 seems to be the magic number. Any less and you might miss some ideas. If you add more people, it slows the process down and there are diminishing returns on the quality of ideas generated.

2. Start by gathering the major user tasks of the project/application in silence - the “things people do”. Each person takes the same coloured post-it and silently writes down one user task per post-it. Once everyone has finished writing their post-its, have each person read their post-its aloud and place them on the table in front of the group. If anyone has duplicates they should be removed at this point.
  • Depending on the size of your application it can take 3-10 minutes to get all the major tasks, but you can watch the body language to see when they are done. You will see that the group goes from huddled in at the beginning to standing/leaning back at the end.
  • Likely each post-it starts with a verb. (eg. Compose E-mail, Create Contact, Add User, etc)
  • These are the high level user stories called “User Tasks” which forms the "walking skeleton" of the map.
  • When they are done, point out to your team that in a few minutes they gathered most of the high level scope and that if they missed a user task or two, someone else probably didn’t. This might be their first ‘aha’ moment for silent brainstorming.

3. Next ask the team to group the post-its in silence. Simply ask them to move things that are similar to each other closer to each other and things that are dissimilar to each other should be moved farther apart.
  • Use silent grouping simply because it is faster than grouping them out loud.
  • If duplicates are found, remove them.
  • Groups will form naturally and fairly easily.
  • Once again, body language will help you see when they are done - usually 2-5 minutes.

4. Using another colour of post-it, name each group and put the post-it on top of the group. This step can be done out loud.

5. Arrange the groups left to right in the order a user would typically complete the tasks.
  • If the group can't decide on an order between two or more tasks, it probably doesn't matter.
  • The groups are called “User Activities” which form the backbone of the map.
  • You should now have the first 2 rows of the user story map - something similar to this:
A1       A2    A3          (user activities = backbone)
T1 T2 T3 T4 T5 T6 T7 T8 T9 (user tasks = skeleton & timeline)

6. Now walk the skeleton to make sure you haven't missed any major user tasks or activities. You can walk through user scenarios, or even bring in users and ask them to walk through their job functions to make sure everything is accounted for.

7. With a finished framework for the map, you can add more detailed user stories below each user task before breaking your map into releases. I like to use the same silent brainstorming technique to generate the initial set of stories for each user task and augment it with other techniques such as user scenarios and personas. Once you have a good set of stories, then you can put your release lines in the map and ask your users to prioritize top to bottom.
  • I like to put the first release line on the map pretty high on the map so that it only allows for 2-3 user stories per user task in the first release. This has been an effective way to encourage prioritization and scoping.
  • Because all the stories end up on small post-its, you can forgo the traditional 'as a' format and just put the story title on the post-its. This will allow you to read the map a little easier.

8. Finally, I like to take all the user stories in the first release and do some serious user story slicing to make sure we have sliced the first release as thin as possible. As a guideline, you should strive to be able to create the whole app (at least one small user story slice for each user task) in the first iteration or two.

"An example would be handy right about now" (Brian Marick)

(click to enlarge)
Here is an example user story map for creating the next email client competitor:
  • The second row contains the "things people do" in an email client such as Compose Email, Send Email, and Create Appointment. 
  • The first row contains the groupings for those things people do. 
  • The first yellow row is the smallest user story slice for each user task. For Compose Email, that means a basic form with To, Subject, and Body text fields plus Send and Cancel buttons. Functionality for RTF support, HTML support, adding attachments, getting email addresses from your contact list etc, are not included in this user story but are included as user stories lower in the map. 
  • The small blue and orange post-its on the larger yellow post-its indicate the status of that user story. The blue ones say "done" and the orange ones say "wip" so that you can see your project status flow down the map.

If we now build the first row left to right before working on any stories in the rest of the map we can deliver all of the basic functionality quickly. This enables us to validate our messaging architecture (i.e. Send an email and then make sure you can Read it). It also allows us to test all the basic functionality in the application end to end so that we can make sure it all works together while getting feedback on whether or not it will solve the business problem. If we were building the very first e-mail client, we could release to the public at this time. Notice also that we did not have a user story for "Delete Contact" in the first release - we don't need to deliver functionality for each "User Task" in each release.

Finally, some definitions:

(click to enlarge)
  • The post-its you create in Step 2 are the User Tasks (blue post-its in the diagram). 
  • The groups and group names in steps 3 and 4 are the User Activities (orange post-its). Jeff calls these top two rows the backbone and walking skeleton of your application. 
  • The user stories (yellow post-its) are organized under each User Task in order of highest to lowest priority for that User Task. 
  • The chronological order of how users will typically use the application goes left to right (Time).

Subscribe to Winnipeg Agilist by Email

Tuesday, February 1, 2011

Iterative Development and User Story Slicing

You may have seen Jeff Patton's slides showing iterative vs. incremental development using the Mona Lisa as an example (slides are here, page 80, 81). Iterative development suggests that you build each feature from the ground up increasing the subjective quality of each feature with each user story that you implement. This method is important for allowing you and your team to narrow in on the final solution rather than designing and understanding it all up front. It also allows you to deliver a full featured application earlier and to use methods like trim the tail to optimize your available budget vs the value that the project is delivering.

Here is a quick discussion on Iterative vs Incremental development:

The diagram to the left shows how a project could be completed using Iterative or Incremental development. In both cases, iterations were used to develop the list of features, but in iterative development we build each feature up a slice at a time rather than a feature at a time. Some of the advantages of iterative development are that it:
  • Allows you to validate your architecture and solution early
  • Allows users to see and test the whole application early
  • Minimizes the affects of change to a feature
  • Ensures important stories are built first
  • Elicits improved feedback on the whole application early
  • Allows you to deliver your application early
  • Discourages "gold plating"
  • It partners nicely with user story mapping (turn the diagram upside down and you have your story map)
Some of the disadvantages are:
  • Your code and design has to be change tolerant
  • You have to be proficient at slicing your user stories
  • You won't know the final solution at the beginning of the project
User story slicing is an important technique in iterative development, but what does this look like in practice? Using Jeff's Mona Lisa pictures as a pattern, I've created a few images that show how a feature like "Send Email" could be completed iteratively.

The first story slice is simply a form with little or no validation with text boxes To, Subject and Body with Send and Cancel buttons. When the user fills in the text boxes and clicks Send an e-mail is sent provided the e-mail addresses entered are correct. But, this e-mail has no extra features like support for HTML formats, RTF, attachments, e-mail priorities, etc. Once this story is implemented, the team will implement similar slices of each feature for Read Email, Create Appointment, View Calendar, Create Task, Edit Task, Create Contact, Edit Contact, etc in order to create a minimalist working model of the whole application.



The next slices of this particular feature would be to implement stories such as implementing Carbon Copy (CC) and taking e-mail addresses from your contact list. You can also see that the form has changed slightly - the Cancel button has been removed and the Send button has been moved to the top.



As we continue to iterate through this feature by adding story slices, the form takes additional shape, adding tool bars and tool bar items. At this point, the application may be finished enough to release to production and start earning revenue for the organization while we continue to add new features and use that revenue to help fund the remainder of the project.



A further release with more story slices implemented:



The final release:



Iterative development is an important tool in your agile toolbox to help your teams deliver early and adapt to change while keeping the project's end goals in mind. User story slicing is one of the important techniques you can use to help make this happen.